Bond Updates

Thank you, Williamston.

Sign at Williamston Middle School thanking voters

 

Bond Updates

January 2026 Update:

  • Construction continued on the softball complex

Views from inside the coaches' box and concession building during construction in January 2026:

Softball Complex Coaches Box as of January 2026
Softball Concession Building Construction as of January 2026
  • Planning continued for upcoming construction projects, including the new Explorer Elementary, high school parking lot paving, and middle and high school flooring

Schematic of the new Explorer Elementary and traffic loop:

Schematic overview of the new Explorer Elementary and traffic loop

New renderings of the Explorer Elementary project:

Explorer Elementary Drainage Basin Rendering
Explorer Elementary Project, Highland and Riverside Intersection

A new tractor purchased via bond funds is utilized to remove snow from school sidewalks:

New Tractor purchased with 2024 Bond Funds, JAN 2026

December 2025 Update:

  • Construction continued on the new softball complex
  • Board of Education approval for the new Explorer Elementary, high school parking lot paving, and middle and high school flooring projects

November 2025 Update:

  • Construction continued on the new softball complex
  • Bid processes were completed for the new Explorer Elementary, high school parking lot paving, and middle and high school flooring

Shingles are added to the concession building at the new WCS Softball Complex:

Softball Complex, NOV 2025

October 2025 Update:

  • Explorer Elementary project out for bid

Updated rendering of Explorer Elementary's main entrance, facing south:

Explorer Elementary Entrance Rendering as of OCT 2025
  • Board of Education approval of Community Pool HVAC Mechanical Equipment
  • Community Pool HVAC project out for bid
  • Flooring selected for Williamston High School and Williamston Middle School
  • Continued progress on softball facility construction

New sod and infield clay installed at the softball facility as viewed from the home dugout:

Softball Facility Construction as of 29 OCT 2025

September 2025 Update:

  • New Mary Marshall Tennis Facility Completed (view the ribbon-cutting ceremony here)

Mary Marshall Tennis Courts (photo courtesy of Jack Schaberg):

Mary Marshall Tennis Facility, Completed September 2025
  • Construction continues on the new softball facility

Softball facility as of September 30, 2025:

Softball facility as of September 30, 2025
  • Exterior and interior colors selected for new Explorer Elementary building
  • Flooring selected for the middle and high schools
  • Mechanical equipment bid for the Community Pool HVAC replacement

August 2025 Update:

  • Mary Marshall Tennis Facility Substantially Complete

Shade structures installed at the tennis facility:

Tennis Shade Structures, 2025
  • Locker and bench installation complete at Williamston High School and Williamston Middle School

New lockers installed at Williamston Middle School:

Middle School Lockers, August 2025
  • Classroom furniture installation is complete at Williamston High School and Williamston Middle School
  • Planning continues for 2026 Bond Projects
  • Field drainage, infield surface improvements, backstop, and visitor dugout construction underway at the softball facility

Williamston Softball Facility, as of August 2025:

Williamston Softball Facility, August 2025

July 2025 Update:

  • Construction continues on the tennis court facility

Mary Marshall Tennis Facility as of July 2025:

Mary Marshall Tennis Court Facility as of June 2025
High Tension Concrete at the Mary Marshall Tennis Facility, June 2025
  • Planning and design work continues for the new Explorer Elementary
  • Summer 2026 Bond Project Planning continues. Projects include Community Pool HVAC, High School Parking Lot Paving and Sidewalk Improvements, and High School and Middle School flooring replacement.
  • Construction Continues at the WCS Softball Complex

Electrical lines are installed to power the new concession building at the softball complex:

Infrastructure Installation at WCS Softball Complex, June 2025
  • Locker and bench installation at Williamston High School completed

Lockers and benches are installed at Williamston High School:

Locker Installation at Williamston High School, June 2025
Benches Installed at Williamston High School, June 2025

June 2025 Update:

  • Construction continues on the tennis court facility

Tennis court work during a concrete pour:

Tennis Court Work, June 2025
  • Site work underway at softball facility
  • Design work continues for the new Explorer Elementary
  • Locker replacement begins at Williamston High School and Williamston Middle School

Lockers are removed at Williamston Middle School:

WMS Locker Replacement, June 2025
  • Classroom furniture replacement begins at Williamston High School and Williamston Middle School

New classroom furniture arrives at Williamston High School:

WHS Classroom Furniture Arrives, June 2025

A new tractor for the maintenance department was made possible by the bond:

New Tractor, 2025

May 2025 Update:

  • Construction begins on new tennis court facility
  • Board of Education approved middle school and high school classroom furniture purchases
  • Board of Education approved softball facility bids
  • Planning continued on Explorer Elementary design and site work

Construction underway at the tennis facility:

Tennis court construction, May 27, 2025

Soil boring drilling at Explorer Elementary:

Soil boring drilling at Explorer Elementary

April 2025 Update:

  • Bid package for the softball facility project published
  • Board of Education presented with bids for middle school classroom furniture
  • Design features selected for lockers and tennis courts

Site work begins on tennis court facility:

Site work begins on tennis court facility, April 2025

March 2025 Update:

  • Bid package for high school and middle school lockers approved by the Board of Education
  • Bid package for the tennis court complex approved by the Board of Education
  • Revisions made to draft Explorer Elementary design concept

A project manager from Christman Company reads a story about construction to elementary students in advance of bond work beginning:

Christman Company representative reads students a story about construction in advance of the bond project work at their school.

February 2025 Update:

  • Bid package for lockers and tennis courts published
  • Bids submitted for locker and tennis court projects
  • Revised drafts of Explorer Elementary design
  • Explorer Elementary staff site visit conducted to provide feedback on design concepts
  • Elementary Campus Dropoff/Pickup loop design concepts introduced to the City of Williamston

January 2025 Update:

  • Bid specifications for the high school and middle school lockers and the tennis court facility finalized
  • First drafts of the new Explorer Elementary and elementary campus traffic patten enhancements developed
  • Engineering site visit to Explorer Elementary and Softball Complex completed
  • Schematics of Softball Complex renovations developed

November - December 2024 Update:

  • Architectural contract with French Associates approved by the Board of Education
  • Design work on Tennis Courts, Lockers, and Softball Facility
  • Middle and High School Furniture review and selection underway
  • Learn more updates by listening to the December, 2024 District Podcast here

October 2024 Update:

  • Topographical Survey Contract with Nowak and Fraus Engineers Signed
  • Site Visit to Assess Tennis Courts, Softball Facility, and Middle School and High School Lockers Completed
  • Bond Rating Assessment Completed via Standard and Poor's Global (A+ Bond Rating Assigned)
  • Bond Sale Completed - Read the Press Release Here

September 2024 Update:

  • Middle and High School Classroom Furniture Audit Completed
  • Middle and High School Band Instrument and Equipment Budget Allocated
  • Phone System Replacement Planning Initiated
  • Soil Borings at Tennis Complex Analyzed
  • Board Resolution Regarding Bond Proceeds Approved  

August 2024 Update:

  • Bond Proposal Approved by Williamston Voters

More information will be posted as it becomes available.